Showing posts with label Energy. Show all posts
Showing posts with label Energy. Show all posts

Tuesday, March 16, 2010

Global Prospective: Solar Industry Learns Lessons in Spanish Sun

Global Prospective: Solar Industry Learns Lessons in Spanish Sun
New York Times, 8-March-2010
Spain is the global leader in producing solar power. Its experience is a cautionary tale for Nepali commentators who advocate using solar power to generate electricity in Nepal.

Two years ago, this gritty mining city hosted a brief 21st-century gold rush. Long famous for coal, Puertollano discovered another energy source it had overlooked: the relentless, scorching sun.

Armed with generous incentives from the Spanish government to jump-start a national solar energy industry, the city set out to replace its failing coal economy by attracting solar companies, with a campaign slogan: “The Sun Moves Us.”

Soon, Puertollano, home to the Museum of the Mining Industry, had two enormous solar power plants, factories making solar panels and silicon wafers, and clean energy research institutes. Half the solar power installed globally in 2008 was installed in Spain.

Farmers sold land for solar plants. Boutiques opened. And people from all over the world, seeing business opportunities, moved to the city, which had suffered from 20 percent unemployment and a population exodus.

But as low-quality, poorly designed solar plants sprang up on Spain’s plateaus, Spanish officials came to realize that they would have to subsidize many of them indefinitely, and that the industry they had created might never produce efficient green energy on its own.

In September the government abruptly changed course, cutting payments and capping solar construction. Puertollano’s brief boom turned bust. Factories and stores shut, thousands of workers lost jobs, foreign companies and banks abandoned contracts that had already been negotiated.

“We lost the opportunity to be at the vanguard of renewables — we were not only generating electricity, but also a strong economy,” said Joaquín Carlos Hermoso Murillo, Puertollano’s mayor since 2004. “Why are they limiting solar power, when the sun is unlimited?”

Puertollano’s wrenching fall points to the delicate policy calculations needed to stimulate nascent solar industries and create green jobs, and might serve as a cautionary tale for the United States, where a similar exercise is now under way.

For now, electricity generation from the sun’s rays needs to be subsidized because it requires the purchase of new equipment and investment in evolving technologies. But costs are rapidly dropping. And regulators are still learning how to structure stimulus payments so that they yield a stable green industry that supports itself, rather than just costly energy and an economic flash in the pan like Spain’s.

“The industry as a whole learned a lot from what happened in Spain,” said Cassidy DeLine, who analyzes the European solar market for Emerging Energy Research, a firm based in Cambridge, Mass. She noted that other countries had since set subsidies lower and issued stricter standards for solar plants.

Yet, despite the pain that Spain’s incentives ended up causing, in many ways they fulfilled their promise, Ms. DeLine said.

“Even though incentives can create bubbles and bursts, without them this industry won’t take off,” she said. “The U.S. is really behind Europe on this, and if we wait until solar is cost-competitive on its own, we may miss the boat and an opportunity to shape the market.”

The most robust Spanish solar companies survived the downturn, have restructured and are re-emerging as global players.

For example, when the government changed course, Siliken Renewable Energy, originally a producer of solar panels, shut its factories for five months and cut its staff to 600 from 1,200. But after shifting its focus to external markets like Italy, France and the United States, and diversifying into solar support services, the company now turns a profit.

“We were a company that banks trusted, so we could make the shift,” said Antonio Navarro, a company spokesman. “But a lot of little companies disappeared.”

The period was particularly difficult because it coincided with the global economic crisis, he said.

To encourage development of solar power and reduce dependence on fossil fuels, Europe has generally relied on so-called feed-in tariffs, through which governments pay a hefty premium for electricity from renewable resources. Regulators in the United States have favored less direct incentives like requiring municipalities to buy a percentage of their electricity from companies making renewable energy, although a few cities and states, most notably Vermont, are experimenting with the feed-in concept.

When it was announced in the summer of 2007, Spain’s premium payment for solar power was the most generous anywhere — 58 cents per kilowatt-hour — with few strings attached.

In retrospect it was far too high. “Everyone from all over the world was installing in Spain as fast as they could, and every biologist who could add was working in solar,” said Pedro Banda, director general of the Institute of Concentration Photovoltaic Systems, one of the research institutes in Puertollano.

Even inefficient, poorly designed plants could make a profit, and speculation in solar building permits was common.

Although Spain’s long-term goal had been to produce 400 megawatts of electricity from solar panels by 2010, it reached that milestone by the end of 2007.

In 2008 the nation connected 2.5 gigawatts of solar power into its grid, more than quintupling its previous capacity and making it second to Germany, the world leader. But many of the hastily opened plants offered no hope of being cost-competitive with conventional power, being poorly designed or located where sunshine was inadequate, for example.

Designs for solar power plants vary. The most common type uses photovoltaic panels to generate electricity. Others, called thermal solar plants, use mirrors to focus the sun’s energy on a liquid that, when heated, drives a steam turbine.

In its haste to create a solar industry, Spain made some miscalculations: solar plants can be set up so quickly and easily that the rush into the industry was much faster than anticipated. And the lavish subsidies inflated Spanish solar installation costs at a time when they were rapidly decreasing elsewhere — in part because of increasing competition from panel makers in China, but also because higher volumes produced economies of scale.

In Spain, the tariff, now adjusted quarterly, is about 39 cents per kilowatt-hour for electricity from freestanding solar power plants, and slightly higher for panels on rooftops.

Germany’s tariff, 53 cents per kilowatt-hour, is expected to fall at least 15 percent this summer, and there are proposals before Parliament to eliminate subsidies for solar plants on farmland.

The bonus payments required to make solar energy financially viable vary, depending on local sunshine and the cost of conventional energy. Experts predict that, possibly by next year, Italy will be the first place where solar-generated electricity will not need subsidies to compete with electricity from fossil fuel. Italy has abundant sun and sky-high energy rates, given that it imports most of its fossil fuel.

Even with the reduced incentives and local economic downturn, the solar industry gave Puertollano something of a face-lift and, potentially, a new economic future. Research institutes there are developing cutting-edge technologies. Unemployment, though now up around 10 percent, has not returned to the 20 percent figure. The city is home to a number of solar businesses: a new 50-megawatt thermal-solar plant owned by the Spanish energy giant Iberdrola created hundreds of jobs.

Although coal mines still dot the landscape and a petrochemical factory remains one of Puertollano’s largest employers, that new solar plant sits just next door, with more than 100,000 parabolic mirrors in neat rows on about 400 acres of former farmland. Clean and white as a hospital ward, it silently turns sunshine into Spanish electricity.

Monday, March 15, 2010

BBC Nepali Service Discussion on Load Shedding

http://www.bbc.co.uk/mediaselector/check/nepali/meta/dps/2010/03/100307_electricit?size= BBC Nepali Service's Mr. Naryan Shrestha moderates a discussion on power shortage and load-shedding with Energy Minister Mr. Prakash Sharan Mahat (प्रकाशशरण महत), Maoist CA member Mr. Hari Rokka (हरि रोक्का) and an energy expert Mr. Puspa Chitrakar (पुष्प चित्रकार) on March 7, 2010.

Wednesday, December 30, 2009

Loadsheding 51 hours a week; 12 hours a day likely from next month

Loadsheding 51 hours a week; 12 hours a day likely from next month
Nepalnews, 30-Dec-09

Nepal Electricity Authority (NEA) has increased the load shedding hours to 51 hours a week starting today.

NEA will cut power in all areas in rotation for seven hours a day for five days and eight hours a day for two days in two slots everyday.

According to chief of NEA's load dispatch centre Sher Singh Bhat, the load shedding hours were increased as the electricity production is decreasing, while the production is falling.

NEA had been cutting power only in the mornings and afternoons so far. From today, it will also cut power in the afternoons.

With the advent of dry season, the water level in the rivers has gone down affecting electricity production. All the hydro-power plants in Nepal except Kulekhani and Mid-Marsyangdi are based on run-off-the-river system.

According to NEA, the demand for electricity across the nation at peak hours is 845 MW, while the supply is only 450 MW.

Going by the current trend, outage timing is expected to rise to 12 hours a day starting as early as January.

Although, NEA and energy ministry officials had been touting the loadsheding hours this year would be limited to 10 hours a day, it is likely power will be cut for as long as 18 hours a day in the driest season, like last year.

The forecast of NEA officials, who had been banking on India to rescue Nepal from its power crisis, failed as India agreed to supply much less power than expected by the Nepali officials.

Wednesday, March 18, 2009

Govt plans to import 500 MW electricity from India, says PM

Nepalnews, 17-Mar-09

Prime Minister Pushpa Kamal Dahal has said the government is preparing to import some 400 to 500 MW of electricity from India in order to address the ongoing power crisis.

Ministers and secretaries had gathered at the PM’s office Tuesday afternoon to discuss solutions to the ongoing power crisis.

The PM also said the feasibility of constructing two 133KVA transmission lines connecting Janakpur-Dhalkebar and Dhalkebar-Kathmandu to import electricity from India would be discussed with other political parties and experts at the meeting, according to Om Sharma, the PM’s press advisor.

The meeting was participated by home minister, finance minister, labour minister, industry minister, and the respective secretaries along with experts in the field.

Meanwhile, finance minister Dr Baburam Bhattarai has blamed the coalition partner UML for the long loadsheding hours.

The plans to install a thermal plant to provide immediate relief to people from load shedding was delayed as the water resource minister was busy in the UML general convention, Bhattarai told journalists at his office Tuesday.

Minister Bhattarai also informed that funds would not be a problem to install such plant. “There should be no load shedding next year,” minister Bhattarai said. “We will install a 200 MW multi-fuel plant and also buy some electricity from India in order to meet the power demand.

Saturday, January 10, 2009

Power outage to hit 16 hrs from Sunday

Power outage to hit 16 hrs from Sunday
ekantipur, 9-Jan-09
PRAGATI SHAHI

Nepal Electricity Authority (NEA) has announced 16 hours load-shedding a day from Sunday, a jump of four hours from the present situation.

Sher Singh Bhat, director of NEA's Systems Operations Department on Friday said, “Due to the receding water level in run of rivers and Kulekhani Reservoir, NEA is not able to meet the demand and there is no option but to increase the power outage time,”.

The total power outage will be increased to 108 hours a week starting Sunday.

However, in order to support the operation of industries in the country, the government has decided to provide electricity to industrial estates declared by the government including Balaju, Pokhara, Bhirahawa, Butwal, Dharan and Biratnagar among others through separate feeders.

According to Bhat, all industrial estates that are under the government will be supplied electricity regularly for five days while the remaining two days of the week will be totally without electricity.

“If a particular feeder is used to supply to both the general public and industrial units, the factories will not get this facility,” Bhat said.

Bhat hopes there will be no further increase after the announcement of the 16 hour-load-shedding per day. “This is the climax of load-shedding for this winter,” he said. As per the new schedule, the NEA will cut power for 16 hours a day for six days a week and 12 hours on one particular day in the week.

He said, the water level in the rivers that earlier supplied 255-MW has now decreased to 230-MW.

Bhat said this schedule will apply in most parts of the country including Kathmandu and other major cities - Biratnagar, Pokhara, and Butwal.

The power outage in Hetauda-Birgunj area will be about 84 hours a week (12 hours a day) and it will be around 40 hours a week in some western districts.

The current morning, day/night and evening time power demand is 550 -MW, 480 -MW and 800-MW respectively. Likewise, supply during the morning, day/night and evening is 260-MW, 260-MW and 326-MW respectively.

According to him, the 70 MW Mid-Marshyangdi Hydro Electric Project will generate electricity in the next two weeks and the government is working to import 80-MW from India through Koshi-Kattaiya transmission line by mid February.

“If the government succeeds in importing the 80-MW from India and the Mid Marsyangdi starts to generate electricity then load shedding hrs will be substantially decreased in the coming months,” said Bhat.

Wednesday, December 31, 2008

Govt planning to add 145 MW electricity to national grid soon

Govt planning to add 145 MW electricity to national grid soon
Nepalnews.com, 31-Dec-08

A top government official has said that the government is looking to adopt some strategies to decrease load-shedding hours, which if successful will relieve the nation from the power crisis that has direly affected all spheres of public life.

Secretary at the Ministry of Water Resources Shankar Prasad Koirala on Wednesday said that the government has already taken necessary initiative to import power from India in order to decrease the load-shedding hours that is tipped to increase from the existing 12 to 16 hours a day.

Koirala, who was speaking at an interaction programme in the capital, revealed that at least 145-megawatt electricity will be connected to the national power grid till the end of Falgun month, hence significantly reducing "load-shedding" that has also brought the industrial sector into a virtual standstill.

He said that 20 MW of electricity will connect to the national power grid from Tanakpur (India) and from Falgun the transmission line damaged by the Koshi floods will be repaired and 40 MW additional electricity will be imported from India.

Similarly, within Magh 35 MW will be connected to the national power grid. Talks have been initiated to import another 65 MW from Farbesgunj, Sitamani and Jayanagar of India, he said.

Koirala also informed that the government is toying with the idea producing electricity from solar, wind and wastes.

He also said that given the current power crisis the nation will have to face load-shedding for five more years. But he said that the government has also come up with special strategies, which if successful, will end load-shedding for ever.

Speaking at the same programme, Surendra Bir Malakar, president of Nepal Chamber of Commerce, said that the load-shedding regime has spelled disaster for industrial sector and it is now a time to declare "industrial crisis" in the country.

"The industrial sector has been completely ruined because of load-shedding. There's no alternative than to declare industrial crisis," he said, adding that the government should immediately come up with alternative method to decrease the load-shedding hours or see the industrial sector collapse.

He said that 40 percent of the country's industries have closed down their shutters due to load shedding, and said more industries are at the verge of closing down if the government doesn't do anything about it. nepalnews.com ag Dec 31 08

Kerosene import highest among POL products

Kerosene import highest among POL products
ArthaExpress, 31-Dec-08

Kerosene is imported in the highest quantity among the petroleum (POL) products. “Kerosene is also the highest sold among POL products,” a report from Nepal Oil Corporation (NOC) said.

A recent data compiled by the NOC reveals that 1,52,167.7 Kiloliter (KL) of kerosene was imported in 2007-08 and 1,55,215.5 KL — a little amazing figure — is sold.

The highest quantity of kerosene imported was during 2001-02, that is 3,90,113 KL and the total sales then was 3,16,381 KL.

According to NOC, the total amount of petrol imported stands at 10,1,624 KL, diesel at 3,03,212 KL and the total Air Turbine Fuel (ATF) import stands at 6,8534.1 KL, while furnish oil (FO) import this year is 2,940 KL, the lowest, and gas import stands at 96,836.8 Metric Tonne (MT). However, the sales figure is amazing as some of the products are sold more than they are imported.

In the year 2007-08 NOC sold 10,0,842 KL petrol; 30,2,706 KL diesel; 15,5,215.5 KL kerosene, 68,938.2 KL ATF; 2,918.78 KL FO and 96,836.8 MT cooking gas.

The total quantity of petroleum products imported in the year 2007-08 stands at 7,25,623 KL and the total sales of the petroleum products stands at 7,27,763 KL that is higher than the total import.

“The difference in quantity between import and sales of petroleum products is due to stocks that NOC maintains,” said Digambar Jha, managing director of NOC.

“Sometimes NOC has stock and it supplies from its stock when necessary,” he added. NOC keeps petroleum products in stock for emergency. “NOC can fulfil the demand when the import is lesser than the supply also due to its stock,” Jha clarified.

“During the month of June and July the import of petrol was less than 50 per cent of the demand and during that period we had stock,” he said adding that such stock is helpful in times of necessity.

Tuesday, December 02, 2008

Nepal Electricity Authority Increases Power Cut

Nepal Electricity Authority Increases Power Cut
Himalayan Times, 2-Dec-08

The Nepal Electricity Authority (NEA) has decided to increase the weekly load-shedding hours with effect from today. The increase would be up to 45 hours from the present 35 hours in parts of the country.

"There will be 45 hours of power cut in a week for all consumers living between Lahan [Siraha District, eastern Nepal] and Lamahi [Dang District, western Nepal]," said a source close to the NEA.

Presently the NEA is facing a power deficit of 80 MW of electricity.

Tuesday, July 29, 2008

Oil exploration permit violates law

Oil exploration permit violates law
eKantipur, 28-Jul-08

The government has not followed the constitutional process while signing agreement with international companies for exploration and production of petroleum in the tarai, experts said here on Monday.

Speaking during a national workshop on "Petroleum Exploration and Legal Compliance", jointly organized by Nepal Bar Association (NBA) and World Wildlife Fund (WWF) the experts said the agreement made by the government are not in compliance with the existing laws.

The government has recently signed agreement for petroleum exploration and production with two international companies -- Texona Resources Company and Cairn Energy -- but has kept the agreements confidential.

"The agreements should not be kept confidential according to the 1990 Constitution as well as the present Interim Constitution 2007," said Bishwa Kanta Mainali, senior advocate and president of NBA.

Similarly, the petroleum agreements should meet the requirements of environment protection with a compulsory legal provision for Environment Impact Assessment (EIA) before the companies are granted the exploration rights, he said.

"However, there has been no evidence of EIA being followed by the government," Mainali said.

According to him, though regulation 10 (1) of Petroleum Regulations, 1985, has stated that a bidder shall not be granted more than two exploration blocks for the petroleum exploration, government has licensed five of the 10 blocks to Cairn Energy.

Meantime, speaking during the workshop, Anil Manandhar, country representative of WWF said, "The provision on environmental protection under the petroleum agreement seems inadequate."

Sunday, July 27, 2008

Nepal's energy emergency

Nepal's energy emergency
Required immediately: more power to meet domestic shortfall and to reduce the trade gap by exporting to India
NepaliTimes, Issue $410 (25-Jul-08 - 31-Jul-08)
By Dewan Rai

Whichever government comes to power, the first thing it will have to start working on will be energy.

In any other country, this would be considered an emergency: Nepal is going through its first-ever monsoon power cuts. This winter load-shedding will go up to 56 hours a week. The generation shortfall will be 35 per cent below demand this December.

Not just this year, Nepal will suffer an average of to 6-8 hours of power cuts a day till 2013 because no new major power generation schemes are coming on line till then except the 70MW Middle Marsyangdi.

The other emergency is Nepal's widening balance of payments gap with India, which reached Rs 96 billion this year because of the higher cost of petroleum imports and falling export. The trade imbalance is expected to grow, and the only way to narrow the gap in the medium term is by launching hydroelectricity export projects immediately.

There will be other benefits from aggressive investments in hydro infrastructure: it will generate tens of thousands of jobs. In their economic masterplan, the Maoists say they want to generate 10,000 megawatts in the next 10 years to meet domestic demand and to export to India. This would require investments at a time when most international companies are wary of doing business in Nepal because of political risk.

Nepal's electricity demand is rising at 10 per cent a year, but could increase if the peace dividend finally spurs economic growth. Domestic investors and community generation schemes could easily add up to 50MW a year. Industry analysts see a role for large foreign joint ventures in projects to export power to India.

They point to the Electricity Act of 1992 that allowed 300MW of power to be generated in six years in the mid-1990s, doubling generation capacity, and say Nepal's new government needs to make a similar breakthrough.

"Ten year ago, no one even wanted to hear about investment in hydropower but now we have investors lining up to put money into this sector," says Gyanendra Lal Pradhan of Butwal Power Company, one of Nepal's new breed of entrepreneurs with stakes in seven hydro projects worth 350MW in pipeline.

"It's simple demand and supply," Pradhan adds, "demand is growing so we need to add supply. But we have to be fast, if we start today we may be able to bring load shedding down to zero in seven years, otherwise this shortage will last till 2016."

The time is right for new investments in hydropower to meet domestic shortfalls and to export to India. The Maoists have expressed a strong commitment to develop the sector, but investors are still wary.

Earlier this year, the government issued licenses to two Indian companies for big budget projects: Arun III (402MW) and Upper Karnali (300MW), both dedicated export projects.

On Monday, the World Bank's soft loan division, the International Finance Corporation announced in Kathmandu that would be financing 25 per cent of the cost of both projects.

The government is re-inviting bids for a storage project on the Budi Gandaki, and a slew of new projects are coming on line that will generate 150MW in the next two years.

The earliest any of the export projects will start selling power to India will be 2015, and that is if work starts right away. The 750MW Australia-Nepal export joint venture West Seti project has been delayed by 10 years and will take another 10 years to be completed.

SN Power is exploring the Upper Tama Kosi II and III (500MW), while NEA, with public shares, is starting Upper Tama Kosi I next year to be completed by 2013.

Some, like Ajaya Dixit of Nepal Water Conservation Foundation, say that Nepal should concentrate on fulfilling domestic demand and promoting value-added industries first before expending time and money on export projects which have long gestation.

"Rather than just sell electricity, it would be better to generate downstream benefits from using electricity," he says, "electricity can be the primary mover of socio-economic progress in Nepal."

Others say meeting domestic demand should go hand-in-hand with exports to India to balance the trade gap. Says Balaram Pradhan of the Nepal Hydropower Association: "We have to produce enough energy for domestic economic growth, but we also need to export electricity to bridge the trade gap."

Sunday, April 27, 2008

Govt gives NOC Rs 500m

Govt gives NOC Rs 500m
ArthaExpress, 25-Apr-08

The government Friday gave Rs 500 million to the cash-strapped Nepal Oil Corporation (NOC) to buy fuel.

“After the release of the money from the government, we are preparing to send it to the Indian Oil Corporation (IOC) Sunday to cut our debt,” said an official at NOC. The government, in the past, provided soft-loans of three billion rupees to NOC, which is currently incurring a monthly loss of Rs 1.35 billion, the largest amount ever.

The government´s financial support has come in the light of failure of NOC to supply petroleum products in sufficient quantities. Petrol scarcity has returned to the Kathmandu Valley. Many pumps are closed. Long queues are becoming normal in the front of the few operational petrol pumps.

Linenda Shreshta of Nepal Petroleum Dealers´ Association said the sole fuel distributor has cut distribution in the range of 50 percent. “Supply has shrunk, while demand has soared,” he said.

Presently, 150,000 liters of petrol, 1800,000 liters of diesel, and 180,000 liters of kerosene arrive in the Valley daily, a volume that falls far short of the demand. NOC has directed all its regional offices to distribute fuel as per the demand of the last year.

An NOC official said as the IOC has deducted supply by 30 to 35 percent, the distribution in the market has also gone down. “Today´s government financial support will be just a small help to pay back the loan to IOC,” said the official. “A sustainable solution should be explored.”

IOC has targeted bringing in 94,800 kiloliters of petroleum products, which cost Rs 5.71 billion. We will run cash short of Rs 2.37 billion, said the official. Global crude oil prices have rocketed to historic highs, reaching US$ 119.90 per barrel Wednesday.

Thursday, April 24, 2008

NEA to continue 42-hrs weekly load shedding

NEA to continue 42-hrs weekly load shedding
eKantipur, 15-Apr-08

Nepal Electricity Authority (NEA) is going to continue the 42-hours weekly load shedding schedule it had been enforcing for months.


People were shortly relieved from power cuts until Tuesday as almost all government and non-government offices, industrial entities and other institutions were closed during public holidays for constituent assembly (CA) polls since April 7.

The NEA was expecting increase in water level due to melting snow in the mountains with the rise in temperature and rainfall in the recent days, but it did not happen.

"When we checked it after resumption of NEA offices on Tuesday, we found no significant improvement in water level in the rivers," said Sher Singh Bhatt, chief of the NEA Load Dispatching Center, adding that therefore NEA would continue the 42-hour-week load shedding schedule from Tuesday itself.

The electricity demand has increased with work at offices and industrial entities resuming on Tuesday.

The water level in the rivers can be expected to increase in a stable way with melting snow in the mountains only after the first week of May, according to him. Until that happens, the current load-shedding will continue.

Hours of power cuts was shortened for the last couple of days as electricity demand significantly decreased mainly after April 9, a day before CA polls were held.

NEA had earlier shortened power cuts from 48-hour-a-week to 42-hour-a-week.

Monday, April 21, 2008

‘Do something, anything to end fuel shortage’

‘Do something, anything to end fuel shortage’
eKantipur, 18-Apr-08

The government should come up with new strategies to end the perennial problem of petroleum scarcity, said officials and trade unionists.

“A solution should be found to prevent fuel shortages in the coming days,” said Baburam Rai, president of the Nepal National Employees Association, Nepal Oil Corporation (NOC) section. “The government is funding the NOC from the budget set aside for development projects. This can't last forever,” added the chief of the Maoist-affiliated trade union.

Rai was speaking at a program entitled “NOC's present status and prospects” organized by the union on Friday as part of its Save the NOC Campaign. He said that if there were other alternatives, they should be explored. If jacking up prices is the only solution, the government should say so, he added.

Purushottam Ojha, secretary of the Ministry of Industry, Commerce and Supplies, said serious reforms should be carried out at the ailing corporation to turn it around.

“The NOC's leakage and technical losses should be minimized,” he said. “Depots should be modernized, and oil transportation costs must be brought down.”

Citing an example of Bangladesh which buys petroleum at cheaper rates from Kuwait in return for its workforce's contribution to the economy, he said Nepal needed to make diplomatic efforts and lobby for similar benefits. “The NOC should develop human resources to deal with such matters,” he said.

Secretary Ojha said that the NOC's losses were mounting because of expanding demand at a time when world oil prices were soaring. He added that the NOC was incurring a deficit of Rs 1.35 billion every month.

Following a series of record highs, oil was traded at above US$ 115 a barrel on the international market on Friday.

The NOC owes Rs 10.69 billion to the government and varied financial institutions. The government has already provided the NOC a soft loan of Rs 3 billion to cover its losses. A source said the NOC was asking for another Rs 500 million from the government to pay its Indian supplier.

The corporation loses Rs 22.53 on the sale of every liter of diesel, Rs 5.84 on every liter of petrol and Rs 16.67 on every liter of kerosene. Likewise, its sales price per cylinder of cooking gas is Rs 352 less than its cost price.

Monday, February 18, 2008

Lack of petroleum products affects normal life in Kathmandu Valley

Bandh hits industries in Morang-Sunsari corridor

Bandh hits industries in Morang-Sunsari corridor
ArthaExpress.com, 17-Feb-08

Indefinite bandhs in Tarai has hit Morang-Sunsari corridor industries hard as they have incurred loss of more than Rs 1000 million.

“The industries in the corridor are incurring a loss of Rs 250 million per day,” the Morang Trade Association (MTA) said. “Eighty per cent of industries in the corridor are already closed due to Tarai bandh,” MTA acting chairman Mahesh Jaju said, adding that some industries at Khanar in Sunsari and Tankisinwari in Morang are operating under a heavy security provision.

“The industries that produce jute, noodles, thread, plastic, soap, biscuit and the rice mills are directly hurt by the bandh,” industrialists said.

“The industries producing consumer goods are hit by the bandh hard,” MTA first vice chairman Moti Dugar said adding that condition of the industries will even worsen in the days to come.

“Condition of jute industries is the worst due to indefinite bandh,” proprietor of Swastik Jute Industry and FNCCI central member Champalal Rathi said.

However, the closure of industries has put less burden on Nepal Electricity Authority (NEA) and it has reduced hours of load shedding in the eastern region.

“As the consumption of electricity has decreased following the closure of industries, load shedding hour has been reduced,” chief at NEA Duhabi Grid, Rajendra Mishra said, adding that the daily seven hours of load shedding has been reduced to four to five hours only.

There is a daily demand of 95 mega watt of electricity in the eastern development region. “And the Morang-Sunsari corridor consumes 40 mega watt,” NEA source said.

Fuel, Power Crisis May Halt City Hospital Services

Fuel, Power Crisis May Halt City Hospital Services
ArthaExpress.com, 18-Feb-08

Hospitals and nursing homes in the capital would be in real trouble if the irregular power supply and fuel shortage persists for two or three days more, so much so that a few ambulances have already been grounded.

Four vehicles of the Tribhuvan University Teaching Hospital (TUTH), used for ferrying more than 1,000 staffers, do not operate services during the day time and only ply at night. Even three ambulances of the TUTH are off the road due to shortage of fuel.

"One ambulance has been ferrying doctors and other staffers," said Dr Mahesh Khakurel, director general of the TUTH, adding that the hospital has written to the Home Ministry and Ministry of Supplies and Commerce urging to put an end to this situation.

At the same time the flow of patients in the hospitals from outside the Valley have also fallen. Earlier, the hospital´s out patient department used to witness a long serpentine queue and issue tickets up to 400 patients on an average daily.

The government hospitals do not have to to bear the brunt of load-shedding as they have the connection of direct electricity lines.

However, the private hospitals and nursing homes are depending on diesel during the power cuts. Though they are operating with the help of generators during power cuts, the diesel shortage in the market is sure to affect them.

"Mechanical equipments and expensive instruments easily get depreciated and this affects the service of hospitals," said Dr Bhola Rijal, president of private health institution. The day is not too far when the hospital services will remain halted if this situation continues, he said. Dr Rijal said the government should consider providing an alternate source of electricity to the private health institutions.

Shankar Oxygen Plant, which had supplied 600 oxygen cylinders a day on an average to the hospitals and nursing homes, just supplied 150 cylinders today. "We received 4,000 litres of diesel through the Ministry of Health and Population. We think the stock would not last after a month," said Prakash Agrawal, employee of the plant.

Meager oil volume enters Kathmandu

Meager oil volume enters Kathmandu
eKantipur.com,17-Feb-08

Banda in tarai brought imports of petroleum products through Raxaul, the largest import point, to a grinding halt for the fifth straight day.

While that prevented replenishment of the stock, Nepal Oil Corporation (NOC), with just about a day's supply in store, distributed meager volume of fuel in the market.

NOC Director Madhav Dhungel told the Post that the corporation distributed a mere 60,000 liters of petrol, 128,000 of diesel and 12,000 liters of kerosene in the Valley Sunday.

"The distribution had become possible only after the corporation received fuel consignments from Amlekhgunj and Bhairahawa," he told the Post.

Except the four dealers who used their tankers to transfer the stock and thus won half the volume of consignment as the government had committed, all the supply was made to the security agencies' and Sajha petrol pumps.

Barring those four private dealers, all private sector operated dealers remained dry and closed throughout the day. The situation prevailed in almost all parts of the country.

Long queues were visible at public refilling stations, while the number of vehicles, particularly passenger vehicles plying on the roads has also gone down substantially. Shortage of cooking gas and kerosene - common household fuels - has seriously hit general consumers.

On the day, NOC had received 60,000 liters of petrol, 128,000 liters of diesel and 36,000 from Amlekhgunj and Thankot. "Efforts are on to bring in more fuel from Bhairahawa and make additional imports from Mugalsarai depot of Indian Oil Corporation (IOC)," said Dhungel.

Officials stated that although the Commerce Minister himself was leading the talks, owners of some 250 tankers operating along Amlekhgunj-Raxaul route continued to refuse to ply their vehicles, citing personal threats received by owners and risks faced by the staff.

Drivers of about half dozen tankers, which were escorted towards Raxaul from Amlekhgunj, absconded at Parwanipur after agitating groups got into a scuffle with security forces on Saturday.

Fuel crunch forces schools to shutdown

Fuel crunch forces schools to shutdown
eKantipur.com, 18-Feb-08

More than a dozen schools have been forced to close down in the capital on Monday due to the crisis in petroleum products.

15 schools of Kathmandu and Lalitpur including Little Angles School, Gyanodaya Bal Batika School, Ideal Model School and GEMS have been forced to shut down.

According to Vice President of Private And Boarding School’s Organisation Of Nepal (PABSON) Lakshya Bahadur KC, the schools could not run schools buses to ferry the students from their homes because of the fuel crisis that has swept the capital.

The entire schools in the capital will be forced to close down from Tuesday if the situation does not improve, he added.

PABSON expressed serious concern over the government’s negligence to the current crisis which has led to schools being shut.

Urging the government for smooth supply of petroleum products, the PABSON has demanded an alternative arrangement to the current fuel supply system.

The government on Friday had assured that normal supply of petroleum products will resume in the capital from Saturday after talks with fuel tanker operators.

The crisis has worsened and the number of vehicles plying the streets in the capital has significantly thinned.

Tuesday, February 12, 2008

India positive on providing Nepal 40 MW

India positive on providing Nepal 40 MW
ArthaExpress.com, 12-Feb-08

India´s Ministry of Power is positive on providing Nepal 40 megawatt (MW) of electricity, which Nepal Electricity Authority (NEA) is looking to import from the Duhabi-Kataiya transmission link, NEA´s Managing Director Arjun Kumar Karki said on Monday.

After India´s leading power trader PTC India Ltd told Nepal last month that it would be able to provide the northern neighbor only 15 MW of the 40 MW India had promised last year, effort was initiated at the government level to procure power.

"Indian government is ready to provide us the full forty megawatts," Karki told parliament´s Finance Committee. "We can import power from Duhabi-Kataiya transmission link," he said. Nepal is already importing 50 MW from the link based on the power exchange agreement between the two countries. Still, consumers are facing up to eight hours of daily power cuts.

On Monday, NEA also wrote to PTC India Ltd requesting it to supply 20 MW of additional power from Tanakpur. "We have found that it is technically feasible to import an additional twenty megawatts from Tanakpur," Karki said.

House panel for customs waiver on CFLs Lawmaker and Former Finance Minister Bharat Mohan Adhikari, who chaired the House panel meeting on Monday, told NEA that the panel would ask the Ministry of Finance to waive off customs on import of Compact Fluorescent Lamps (CFLs), which use only a quarter of the power used by traditional light bulbs to provide the same degree of illumination.

"We will ask the ministry to waive off customs for CFLs and also to provide a revolving fund to NEA to make consumers switch from traditional lighting bulbs to CFLs," said Adhikari.

For demand management, NEA is immediately starting distribution of leaflets to consumers, through its billing staff, explaining the benefits of CFLs as well as a scheme to allow consumers to switch to CFLs with zero initial investment.

NEA has proposed that it be provided a revolving fund of Rs 500 million so that it can buy CFLs, install them in people´s homes for free, and pay CFL suppliers in installments from consumers´ bills. Switching to CFLs will reduce electricity consumption of individual households. NEA will continue to charge consumers an average of their past electricity bills for as long as the margin between their past bills and actual consumption do not pay back all the installments of CFL.

The NEA has also asked the house panel to raise customs on power inefficient inverters, make it mandatory for factories not to operate during peak hours, and to expand the adoption of CFLs in government offices and street lamps.

Proposal to supply 250 MW to Nepal

As a longer-term solution to Nepal´s power crisis, India´s Infrastructure Leasing and Financial Services (IL&FS), which is partnering with NEA to build four high-voltage transmission highways across the Nepal-India border, recently proposed to NEA to supply up to 250 MW to Nepal from a 500 MW thermal plant it is setting up in India, Karki told the house panel.

"I Think this is a workable proposal," said Karki.However, the arrangement will come into effect only by 2010 end as it will take three years to set up the plant.

IL&FS has proposed to supply power at IRs 2 to IRs 2.50 per unit. According to NEA´s forecast, the country will face progressively worse power cuts for at least the next five years, after which projects in the pipeline are expected to start plugging the demand-supply gap.

Sunday, February 10, 2008

Power cuts, diesel crunch clobber economy

Power cuts, diesel crunch clobber economy
eKantipur.com, 1-Feb-08
BY MILAN MANI SHARMA

Extended hours of power cut and an unprecedented shortage of diesel - the major industrial fuel - have threatened almost all vital sectors of the economy.

Energy crisis has forced some transport, manufacturing and service units to close down and compelled many others to operate below capacity. Hoteliers lamented that they are finding it tough to keep the guests warm and in illuminated surroundings.

As the country reels under eight hours of daily load-shedding, Rakesh Rawat, general manager of Everest Hotel, said he had to invest additional money and manpower to arrange diesel for the generator to light up the hotel, operate the lifts and keep the central heating system humming.

"Worse, load shedding hours are increasing steadily and it is difficult to obtain diesel," Rawat told the Post. His hotel currently requires 500 liters of diesel a day to keep itself going.

The problem runs equally deep for other hotels, said Prakash Shrestha, president of Hotel Association Nepal (HAN). HAN officials added that some hotels and resorts are organizing city tours for their guests to tide over the cold hours and organizing candlelit dinners in an attempt to make those times 'exciting'.

Almost all of manufacturing industry has cut production and rescheduled operating hours. Some outfits like state-owned cement manufacturer Hetauda Cement Factory and Reliance Spinning, a manufacturing unit in Biratnagar, have closed down operations.

Arati Strips, a leading export-oriented industry in the eastern region, has curtailed production hours.

"The problem has hit all of manufacturing industry -- small to large -- equally," said Kush Kumar Joshi, second vice president of the Federation of Nepalese Chambers of Commerce and Industry (FNCCI).

The crisis has not spared development activities either. According to Shakuta Lal Hirachan, president of Nepal Contractors Association, large scale construction work has been put off due to the energy crisis.

"It threatens to raise the cost of construction by 20 percent," he warned.

As the shortage of diesel has become really severe over the past week, the number of vehicles plying the roads has gone down - both in Kathmandu Valley and on the major highways. Many were seen queuing up at petrol pumps at Bhadrakali, Baneshwor, Naxal, Pulchowk and Kalimati Friday.

Nepal Transport Entrepreneurs Federation (NTEF), which has issued strike threats, says strike or no strike, no public vehicle and goods carrier can ply the roads if the shortage persisted.

Still more unnerving, NOC says it has just about two days' supply in stock. "At the Thankot depot, we are down to our emergency stock," said an official there.

NOC deputy chief Umesh Dahal said it was running low on major petroleum products-especially diesel- as the corporation has not been able to make payments in time to ensure that adequate oil shipments kept arriving regularly.

Although the government on Thursday released one billion rupees to NOC to finance immediate imports, officials said that with losses amounting to Rs 600 million a month, the money wasn't going to bail the corporation out of the current crisis. At best, it will stave off the crisis for a few weeks.

The government did try to trim the deficit by raising prices for diesel, kerosene and cooking gas last Monday, only to backtrack within 48 hours following violent demonstrations.

With its diesel stocks depleted and the corporation strapped for cash to finance regular imports, NOC over this week supplied just about half the volume of normal diesel demand in the Valley. "Load-shedding has put extra pressure on us," said Ichchha Bikram Thapa, NOC spokesperson.

While sluggish hydropower development has made power-cuts an inevitable phenomenon, lack of prudent policies and shelving of plans to liberalize the petroleum sector till the Constituent Assembly election are certain to keep the country staggering from one fuel crisis to another.

"The government has to work on a sustainable way out. It simply cannot let the problem deepen and affect the economy," said HAN president Shrestha.

The only solution at present seems to be pouring in more money from government coffers. "That will cause a crack on the fiscal front," say Finance Ministry officials. But they also acknowledge that there seems to be no alternative, at least in the short run.